Are there notable labor or working wage considerations involved?

“Yes. Based on the involvement of the Maryland Stadium Authority (MSA), a prevailing  

wage chart for the project will eventually be generated.  

(https://mdstad.com/projects/prince-georges-county-blue-line-corridor-sports-and-entertainment-facilities-feasibility).” 

The Prevailing Wage law applies to any public work project including school construction where the contract value is $250,000 or greater and (1) the State or an instrumentality of the State is the contracting body and there is any State funding for the project; (2) a political subdivision is the contracting body and 25% or more of the money used for the construction is State money; or (3) a political subdivision is the contracting body for the construction of an elementary or secondary school and 25% or more of the money used is State money. (https://www.dllr.state.md.us/labor/prev/prevwagefaqs.shtml#1